Grand Haven Light & Power
This project took place in early 2004 and involved an outage to install new Low NOx burners and overfire air ports. This job was on a fast track; 19 days. IMTC-MEI rebuilt three mills with upgraded classifiers, rebuilt all burner throats, and made also made repairs in the windbox from previous fire damage.